| Weekly Construction Calendar |
| Tuesday, July 27: |
- Electricians: 321 S. 42nd rough in
- Jessica/Dismas:
- Tim/Dismas Team:
- Joy Out
|
| Wednesday, July 28: |
- Chuck's Team: 4926 Wheatley; 1227 S. Clay
- Framing Crew: 540 Caldwell pour footer
- Holm Team: 2722 Greenwood windows, doors
- Paint Crew: 1626 Gallagher doors, trim
- Rehab Team:
- Tim/Dismas:
- Trim Crew: 1626 Gallagher interior trim
- Joy Out
|
| Thursday, July 29: |
- Chuck's Team: 1227 S. Clay; 321 S. 42nd; 4926 Wheatley
- Dream Machine: 1460 S. 9th prep for dedication; 2211 Woodland siding
- Framing Crew: 4926 Wheatley pour flatwork
- Holm Team: 2722 Greenwood windows, doors
- Rehab:
- Richey (& Dismas Matt): 1827 Gaulbert exterior sheath
- Trim Crew: 1626 Gallagher kitchen cabinets
- Veech/Women for Habitat: 2342 W. Madison siding, soffit
- Joy Out
|
| Friday, July 30: |
- Coakley: 3510 Herman form concrete
- Cox: 1626 Gallagher build shed, install hardware
- Dream Machine: 1460 S. 9th prep for dedication; 2211 Woodland siding, paint
- Framing Crew: 4926 Wheatley pour flatwork; 3510 Herman pour flatwork
- Layout Crew: 540 Caldwell for block
- Richey: 1827 Gaulbert sheathing, blueboard
- Joy Out
|
| Saturday, July 31: |
- Chuck's Team: 1227 S. Clay; 4926 Wheatley
- Coakley: 3510 Herman
- Cox: 1626 Gallagher paint, trim, caulk
- Dream Machine w/ Siemens Team Build: 2211 Woodland paint
- Landscape w/ Aerotek: TBD
- Veech w/ Women for Habitat: 2342 W. Madison
- Joy Out
Lunch graciously provided by Church of the Advent - Thank you!
|